KFC in Colesberg

KFC in COLESBERG
The KFC Head Office was impressed by the quality of the finishes and construction speed.
A present KFC fast food franchise decided to increase its footprint of stores in the Northern Cape. After researching alternative building methods he chose Light Steel Frame for their outlet located in Colesberg. The building method would achieve their goals for an energy efficient building, reducing the carbon footprint, whilst providing a building solution that offers a modern fresh approach to create working space, with the benefit of contributing towards a sustainable environment.
A raft foundation was cast with pre-mix concrete that was trucked in from 140 km away. The Light Steel frame wall panels and roof structure were erected in only five days which was followed by the walls that were clad externally and internally in a record 6 days. The total superstructure only took five weeks to complete.